Production Readiness & PO Closing Control Tower

From Material Readiness to On-Time Production

Sunday, 20 Sep 202608:09 WIB
🔔3
MN
Muhammad Lukman N.Management Trainee
Open PO45

▼ -24.3% vs 1 Sep (111)

!
Overdue PO39

▲ 46.4% of total PO

PO Commit (Sep)85,493
Actual Closed (Sep)128,047

▲ +50.0% vs Commit

Commitment Achievement150%

Actual / Commit

Closing Accuracy72%

On-time Closing

Open vs Overdue PO Trend

PO Status Distribution

Top 5 Overdue by Model

Overdue by Aging (Days)

PO Support Needed (Material Readiness)

View All
StatusPO#CellModelArticleCRDPlan QtyFGIN Bal.Critical MaterialReadinessDays LeftPIC
Overdue 0903098765B03SL 72SL070214-Sep-26 700-280Outsole
10%
-6WS B03
Overdue 0902992340B01Handball SpezialLA030116-Sep-26 1,200-450Outsole, Laste
85%
-4WS B01
Overdue 0903011123B05SambaSA010216-Sep-26 800-320Heelpatch, Lace
40%
-4WS B05
Overdue 0903120011B02Handball SpezialLA030219-Sep-26 1,100-180Leather
70%
-1WS B02
Open 0903056789B12GazelleGA050120-Sep-26 1,600-220Laste
60%
0WS B12
Open 0903120012B15SambaSA010321-Sep-26 950-120Toe Cap
70%
1WS B15
Open 0903078901B08CampusCA030322-Sep-26 900-150Eyestay
75%
2WS B08

Material Readiness (All PO)

View Detail
Leather
72%
Eyestay
65%
Toe Cap
60%
Heelpatch
58%
Vamp Lining
76%
3 Stripes
82%
Lace
54%
Insole
68%
Outsole
42%
Sockliner
70%
Inner Box
80%

Production Readiness by Cell

Water Spider Task (Today)

View All
TimeTaskPO#MaterialFromToStatus
08:15Pick Material0902992340OutsoleColocB01On Process
09:30Transfer0903011123LaceWHB05Arrived
10:10Pick Material0903056789LasteWHB12Pending
11:00Transfer0903078901EyestayColocB08Pending
12:20Pick Material0903098765OutsoleSupplierB03Delayed

Recent Issues & Escalation

View All
TimeCellIssuePICStatus
12:00B08Manpower allocationProductionClosed
11:20B03Late material arrivalLogisticOpen
10:05B12Machine downtimeMaintenanceOn Process
09:45B05Laste shortageWS B05Follow Up
09:10B01Outsole not readyWS B01Open